Promoting collaborative working within the construction industry
This section provides a guide to planning, preparing and issuing production drawings. For ease of reference a key to the sections is given in the Table below, with an indication when the actions should be carried out within the project process.
|
Section |
Item |
Actions |
Project Stage |
|
Standard Methods and Protocols (SMP) |
Produce Office SMP Agree Project SMP |
Scheme design |
|
|
Scope, arrangement and format |
Prepare Drawings Schedule Determine arrangement of drawings set Determine format of drawings set Prepare Drawings register |
Detailed design |
|
|
Production sequence |
Prepare Production Plan |
Production information |
|
|
Time and resource programming |
Prepare Time and Resource Plan based on Production Plan |
Production information |
|
|
Revisions to drawings |
Control the revision process Clearly note all changes |
Production information |
|
|
Document and data management |
Establish office and project drawing management procedures |
Production information |
|
|
Roles and responsibilities |
Define and allocate the roles Ensure responsibilities are backed with authority |
Scheme design |
Irrespective of whether the Drawings Overlay or Model Exchange method described in Section 2.3.4 is adopted, effective collaboration and re-use of data within a diverse group of designers and specialist constructors depends on establishment of an agreed electronic method of producing the drawings, together with a commitment to the discipline required to make it work. Design team agreement on Standard Methods and Protocols (SMP) should be reached at an early stage to allow consistent application throughout the project. This agreement should be formalised as the Project SMP. It should cover:
In establishing the Project SMP the main problem to overcome is likely to be the exchange of CAD data between disparate CAD systems in the project team
There is a need to establish an Industry SMP for collaborative working using CAD. In the absence of such a Standard, design offices should establish an Office SMP incorporating the recommendations in this Code and BS 1192 Part 5. Design offices that work together on a regular basis should consider harmonising their respective Office SMPs so that the agreement of Project SMPs can be facilitated. The establishment of an Office SMP will offer wider advantages, e.g. transfer of data between projects, greater technical control, and training of new and transient staff.
The Project SMP (and Office SMP) will cover all or some of the following:
The Project and Office SMPs may be extended to cover relevant specification issues:
To establish the Project SMP it may be appropriate to issue a questionnaire to all members of the design team - a sample questionnaire is given in Appendix D4. An example Project SMP contents list is given in Appendix D5. In practice it is likely that the main areas for discussion will be the file naming convention and layering standards.
It may not be possible to agree every detail of the Project SMP at once, but this should not prevent partial agreement followed by completion later. The Project SMP should, like any other serious piece of project information, be subject to revision control because it is clearly essential that all parties hold, and work to, the up-to-date agreed version.
Compliance with the Project SMP should be checked using appropriate software, so that the integrity of the structure and content of the information within the electronic files can be assured. Commercial software is available for this purpose.
Before detailed planning of production can take place, the drawings required for the project need to be decided and set down in a Drawings Schedule (see Figure 2.14). All drawings to be prepared by all design disciplines should be included. Preparation of the schedule will involve close consideration of the proposed building, the nature of its construction and the number of model files required for coordination, together with the following:
|
Building parts |
Notes |
Drawings |
|
Floors and galleries |
2nd to 4th repeated layout |
4 No. plans |
|
Stairs and ramps |
3 x 2 No. Type conc. |
2 No. GAs, 4 No. Details |
|
Roofs |
Upside down details as DSS job |
1 No. Plan, 6 No. Details (standard) |
|
Frame |
Co-ord with structural engineer |
8 No. Details |
|
External wall openings |
6 No. Window types |
Window schedule |
|
|
Standard linings |
Door schedule |
Figure 2.14 Example drawings schedule (part of)
The Drawings Schedule should then be developed into a Drawings Register, listing the complete set of production drawings, with numbers, titles, etc.
As far as possible, detailed design of the building should be complete before production information is commenced, and drawings and specification should be complete before tender action and construction. However in practice the preparation of production information will often overlap both detailed design and construction.
Sometimes overlap can be advantageous, for example in compression of overall project programmes and making best use of the design skills of specialist constructors. But overlap can also give rise to poor technical and dimensional coordination resulting in wasteful reworking and defects.
Design is a highly iterative process, with many complex dependencies between elements and many 'review and revision' cycles. A basic principle is that the production information for any given element or type of work must be free from subsequent design dependencies before it is prepared and used for construction.
This principle should be fundamental to the preparation of a detailed Production Plan for the preparation of the drawings listed in the Drawings Register. The plan should follow the principle of multi-disciplinary build-up of drawings described in Section 2.3.4. It should consist of a sequential series of actions, each stating the information to be added, in order to guard against omissions and wasteful 'backtracking' during preparation of the drawings.
The plan should thus define the required model files, structured to give the required degree of flexibility and potential re-use of the information. The transfer of files from one design discipline to another should be shown, together with the times for drawings overlay checking (if used, see Section 2.3.4). The plan should take into account the required sequence for completion of drawings for 'work packages', if used. The completed plan should be checked to ensure that it provides for the completion of all drawings in the Drawings Register.
The multi-disciplinary build-up of drawings follows a similar pattern from project to project, and there will be much commonality between the Production Plans for different projects of similar type and size. Design offices may find it useful to prepare template checklists to help ensure that all items of information to be added at each stage are remembered. Wherever possible such templates should be multidisciplinary.
The Production Plan (see Section 2.4.4) should have determined the optimum sequence for preparing the drawings, and this should be the basis for allocation of resources and programming. These decisions will be based on the availability of suitably skilled personnel from the various design team organisations, and the requirements of the overall project programme. The outcome of this process should be a Time and Resource Programme (see Figure 2.15).
Historically, detailed programming has been based on estimates of time for each drawing, but this will be unrealistic for the multi-disciplinary build-up procedure recommended in Section 2.3.4. Estimating should be based on the activities set out in the Production Plan, grouped together as required to give an appropriately coarse 'grain' to the programme. A simplified but basically sound programme is far more valuable than a highly detailed but cumulatively inaccurate one.
The programme should make appropriate allowance for the detailed design and documentation inputs of all consultants and specialist constructors, and should be coordinated with the programme for producing the specification. It should be agreed with all parties, including the managing constructor (if known).

Figure 2.15 Simplified Time and Resource Programme
In order to make the change to the multi disciplinary Model Exchange method described in Section 2.3.4, normal planning of drawing production giving total number of drawings, production time and resource allocation should be used in the early stages of learning. However, as experience of the method is gained it will become apparent that drawing production is delayed whilst the model files are established and co-ordinated. The delay is more than compensated for by the generation of a large batch of good quality drawings in a short space of time. This is because the final stage of drawing activity consists of simply selecting, saving and annotating views and filling in title blocks. This methodology does not limit the drawing set to the initial Drawings Register: further drawings at greater or lesser scales can be produced swiftly from the same data. Experience will lead to improved time and resource programming.
All parties involved in a project should use the current version of drawings, both precontract and during construction. The Drawings Register identifying all drawings prepared by all parties and all revisions thereto should be updated constantly, and reissued to all affected parties. At the end of the project this should become the register of as-built drawings.
CAD systems facilitate the revision process, and there will always be the temptation to re-issue drawings in response to the smallest site queries and design changes. It is important to establish a thorough change approval process to control this, so that revisions are made only when appropriate.
It is most unhelpful if the revisions notes on a drawing are insufficiently specific, e.g. 'General revisions'. CAD software enables revisions to be highlighted by clouds and text on a separate layer, and these should be used to identify the parts of the drawing that have changed. The revision reference should be attached to the cloud and the revision box text should give a concise description of the revisions carried out - see Figure 2.16.
This Section deals with the collection, management and dissemination of data in the office and throughout the project. It emphasises the importance of good communication and a managed method of dissemination that will promote the production of better quality production information. Although the Section concentrates on the management of drawings, its recommendations apply equally to the management of specification and other documents.
Figure 2.16 Example title block with revisions
Control of the project is, in essence, control of the project information. To achieve this control a disciplined approach to the management of information is essential. There are basically two ways of establishing control; first, the simple method by translating good paper based practice to IT and, secondly, using a range of current Internet collaboration tools.
In essence this is a filing cabinet based approach to IT. Data is stored in folders and sub folders according to need.
The first requirement is a Local Area Network (LAN) and an Internet e-mail facility. A LAN would typically be a minimum of 4 or 5 PC's linked to a PC acting as a central file storage unit. A single storage unit will hold the current, up to date data for all projects in the practice, simplifying the data back-up and retrieval procedures.
The system should include an issue and receipt procedure for data. This could be an electronic version of a simple paper based system in the form of a spreadsheet recording the current project situation, what is available, what has been received, what has been issued. See Figure 2.17 for a typical example.
If information is issued without the ability for tracking and auditing, no-one will know the current status of the information in their possession. Each drawing or data file must be issued with a purpose for use, that is:
Displaying the production programme milestones, thereby showing current delivery status could further enhance the spreadsheet.
Where there are several design teams involved in the project the management methods should be expanded to cover collection, management and dissemination of all relevant project information. This should also include the delivery of health and safety, operations and maintenance and facilities management requirements.
An extranet is often used for this purpose, but should not be viewed merely as a repository for drawings, rather as providing the facility to audit and report on the project status at any given point. It should not be operated as a reactive process (i.e. 'drawings are available if you want to look at them'), but more as a proactive process, where information is delivered and its receipt registered.
It is unlikely that a single system or piece of software will cover the project requirements for drawing management, document management and collaboration. A suite of complimentary tools may be required for the needs of the design and construction teams. Considerations include:

Figure 2.17 Example Drawing Register and Issue Sheet
Underlying the data management software should be a single source of approved project information, which contains the latest approved data accessible to all authorised personnel. Avoid at all costs a data ‘dumping ground' and the traditional approach of each member being responsible for sending information to whoever is thought to require that data.
Guidance on this subject can be found in 'Project Collaborative Extranets for Construction - A Guidance Note' prepared by the CICA.
In the electronic age, traditional roles within the design team do not alter radically, but there is a need for more thorough and detailed management of the design and documentation process. Responsibility for this overall management should lie with the Design Team Leader.
The role of Design Team Leader is best held by the designer having responsibility for interpreting the client’s requirements, articulating these into a primary physical form and producing the major parts of the project specification. For most building projects this will be the architect.
Many of the roles and responsibilities of the Design Team Leader, especially on larger projects with several design disciplines, require expertise in IT particularly:
The Design Team Leader may have these skills personally, or may rely on a suitably qualified person from his office, or even an external consultant. On large projects document management may require special skills, justifying the appointment of a Document Manager, from the Design Team Leader's office or elsewhere.
The main roles and responsibilities of the parties are: